Project Overview
Accelerated construction of a CNG fueling station for a new transit-bus fleet in Corpus Christi.
EFS West was selected by the Corpus Christi Regional Transportation Authority to construct a CNG fueling station at its transit-bus maintenance yard.
The project included three 1,500 SCFM ANGI compressors, a PSB dryer, three storage vessels, six transit dispensers and a new emergency backup generator.
An accelerated schedule was required to accommodate the arrival of the agency’s new CNG bus fleet. Construction was completed in approximately three months, from August through November 2012.